HOW TO CALCULATE CRITICAL PATH, FREE FLOAT AND TOTAL FLOAT ?

Contributed By:
Critical Path Method

Activity
Predecessors
Three time Estimates


a
m
b
A
---

2

B
A

5

C
A

10

D
A

6

E
B,C,D

9

F
E

4

G
F

3


here we have not putted the values of a and b as it is not required in calculating the critical path, free float and total float.

Step-1: Draw Network Diagram




Step-2: Find Critical Path


P1: A > B > E > F > G = 23
P2: A > C > E > F > G = 28 -> Highest time = critical path
P3: A > D > E > F > G = 24

Step-3: Calculate Early start, late start, early finish and late finish.

SHOWN IN THE DIAGRAM.

Step-4: Calculate Total float and free float.


TOTAL FLOAT=LATE START - EARLY START



Total Float (TF)                                                                   

A
0-0=0
 B
7-2=5
C
2-2=0
D
6-2=4
E
12-12=0
F
21-21=0
G
25-25=0












FREE FLOAT OF A ACTIVITY= EARLY START OF NEXT ACTIVITY - EARLY FINISH OF CURRENT ACTIVITY

Free float (ff)
A
2-2=0
B
12-7=5
C
12-12=0
D
12-8=4
E
21-21=0
F
25-25=0









1 comment:

  1. The Education Loans in India is a good choice for students who do not have enough money to pay full term fee. With the help of different education loan schemes many student are acquiring higher education in India and all around the world. With the help of banking sector student achieve your goal.