Critical Path Method
Activity
|
Predecessors
|
Three time
Estimates
|
||
|
|
a
|
m
|
b
|
A
|
---
|
|
2
|
|
B
|
A
|
|
5
|
|
C
|
A
|
|
10
|
|
D
|
A
|
|
6
|
|
E
|
B,C,D
|
|
9
|
|
F
|
E
|
|
4
|
|
G
|
F
|
|
3
|
|
Step-1: Draw Network Diagram
Step-2: Find Critical Path
P1: A > B > E > F > G = 23
P2: A > C > E > F > G = 28 ->
Highest time = critical path
P3: A > D > E > F > G = 24
Step-3: Calculate Early start, late start, early finish and late finish.
SHOWN IN THE DIAGRAM.
Step-4: Calculate Total float and free float.
TOTAL FLOAT=LATE START - EARLY START
Total Float (TF)
A
|
0-0=0
|
B
|
7-2=5
|
C
|
2-2=0
|
D
|
6-2=4
|
E
|
12-12=0
|
F
|
21-21=0
|
G
|
25-25=0
|
|
Free float (ff)
A
|
2-2=0
|
B
|
12-7=5
|
C
|
12-12=0
|
D
|
12-8=4
|
E
|
21-21=0
|
F
|
25-25=0
|